Phase II of Intermediate Terminal and Riverfront Access Project beginning March 6


Demolition begins Monday, March 6 to remove the 4-foot concrete warehouse foundation for the IntermediateTerminal.and Riverfront Public Access Project. The second phase also includes grading, seeding and refurbishing the Terminal Dock. At completion the dock will be ready to receive cruise ship traffic.

Phase II is expected to be completed by June.  

Ahead of Phase III, as part of the Riverfront Master Plan, a public meeting will be scheduled in the near future to present conceptual options for the Terminal Dock and Lehigh Property. The improvements at both the Terminal Dock and Lehigh properties are expected to provide public park space and public riverfront access.

Phase I, which included structural restoration of the Terminal Dock, was completed last December.

The project budget of $2,944,318 is being funded with Capital Improvement funding.